+ | * Jim | ||
+ | ** Compile needed data files | ||
+ | ** Code web UI | ||
+ | * Cartik | ||
+ | ** Load data files into DB | ||
+ | ** Write Restlet web services to return query results (with Jim) | ||
==Week 4 (Sep. 15-19)== | ==Week 4 (Sep. 15-19)== |
Revision as of 15:19, 26 August 2008
Detailed plan for database and web UI prototype development.
Contents
Week 1 (Aug. 25-29)
- Hilmar, Jim, Cartik - develop this plan
- Jim
- create Eclipse project for Phenoscape web UI at Phenoscape Sourceforge site
- define OBD query requirements and deliver to Cartik
- complete EQ and matrix import/merge functionality for Phenex
- Cartik
- empty current data from DB
- work out reliable protocol for reload of ontologies and annotations using scripts
- run reasoner on DB
Week 2 (Sep. 1-5)
- Jim
- out on vacation most of the week.
- Cartik
- continue DB data loading work
- OBD API query implementations
Week 3 (Sep. 8-12)
- Jim
- Compile needed data files
- Code web UI
- Cartik
- Load data files into DB
- Write Restlet web services to return query results (with Jim)