Difference between revisions of "Project Plan"

From phenoscape
Line 11: Line 11:
 
* Authors can update datafiles.  The [[Versioning|versioning system]] will be supported by DOIs and data citation conventions.
 
* Authors can update datafiles.  The [[Versioning|versioning system]] will be supported by DOIs and data citation conventions.
  
=== Anatomy ontology coordination===
+
==Anatomy ontology coordination==
  
 
'''Target release date:''' December 20, 2011
 
'''Target release date:''' December 20, 2011
Line 18: Line 18:
 
* Detailed citation storage/export (migration to the version 3 metadata model).
 
* Detailed citation storage/export (migration to the version 3 metadata model).
 
* Authors can [[Coauthor PIN|delegate submission authority]] to co-authors or other collaborators.
 
* Authors can [[Coauthor PIN|delegate submission authority]] to co-authors or other collaborators.
 +
 +
==Homology reasoning==
 +
 +
 +
==Phenoblast and OBD/OWL==
  
 
[[Category:Project Management]]
 
[[Category:Project Management]]
 
[[Category:Software]]
 
[[Category:Software]]

Revision as of 15:28, 11 August 2011

Project components

Much of the schedule is based on the 2007 NSF grant, with amendments by the Dryad Consortium Management Board and subsequent grant commitments. For Dryad project developers and associates, a (private) detailed development plan is available. For completed releases, see the Release Notes. The original project plan is still available.

Scalable workflow

Release 2.0 - 2nd quarter

Target release date: June 30, 2011

Data deposition:

  • Authors can update datafiles. The versioning system will be supported by DOIs and data citation conventions.

Anatomy ontology coordination

Target release date: December 20, 2011

Data deposition:

  • Detailed citation storage/export (migration to the version 3 metadata model).
  • Authors can delegate submission authority to co-authors or other collaborators.

Homology reasoning

Phenoblast and OBD/OWL