Difference between revisions of "Data Jamboree 2/Prototype"
From phenoscape
(→Week 1 (Aug. 25-29)) |
(→Week 1 (Aug. 25-29)) |
||
Line 3: | Line 3: | ||
==Week 1 (Aug. 25-29)== | ==Week 1 (Aug. 25-29)== | ||
* Hilmar, Jim, Cartik - develop this plan | * Hilmar, Jim, Cartik - develop this plan | ||
− | * Jim | + | * Jim |
− | * | + | ** create Eclipse project for Phenoscape web UI at Phenoscape Sourceforge site |
− | * | + | ** define OBD query requirements and deliver to Cartik |
+ | ** complete EQ and matrix import/merge functionality for Phenex | ||
+ | * Cartik | ||
+ | ** empty current data from DB | ||
+ | ** work out reliable protocol for reload of ontologies and annotations using scripts | ||
+ | ** run reasoner on DB | ||
==Week 2 (Sep. 1-5)== | ==Week 2 (Sep. 1-5)== |
Revision as of 15:15, 26 August 2008
Detailed plan for database and web UI prototype development.
Contents
Week 1 (Aug. 25-29)
- Hilmar, Jim, Cartik - develop this plan
- Jim
- create Eclipse project for Phenoscape web UI at Phenoscape Sourceforge site
- define OBD query requirements and deliver to Cartik
- complete EQ and matrix import/merge functionality for Phenex
- Cartik
- empty current data from DB
- work out reliable protocol for reload of ontologies and annotations using scripts
- run reasoner on DB
Week 2 (Sep. 1-5)
- Jim - out on vacation most of the week.